Construction over I-235 will require highway closure

I-235 and 13th Street Project (Courtesy: KDOT)
I-235 and 13th Street Project (Courtesy: KDOT)

WICHITA, Kansas – Placement of 12 steel bridge beams over I-235 at 13th Street will require a weekend closure of I-235 between Central Avenue and Zoo Boulevard starting on Friday, April 25.

The closure will begin at 7 p.m. on Friday evening and the two-mile section of I-235 should reopen on Sunday night, April 27.

A detour will direct interstate traffic to West Street using Central and Zoo Boulevard.

All northbound traffic will exit at Central, travel 1½ mile to West Street, travel north then turn left onto Zoo Boulevard and return to I-235 via the northbound ramp.

Southbound traffic will be directed using the same city streets.

The Kansas Department of Transportation highway interchange project adds a ramp from eastbound 13th Street east of Ridge Road to southbound I-235 and a ramp from northbound I-235 to westbound 13th Street.

The project is expected to reduce traffic congestion at the I-235 and Zoo Boulevard interchange and will add another route for crossing the Wichita – Valley Center Floodway.

Dondlinger & Sons Construction Co. of Wichita is the lead contractor on the $23,111,124.58 project.

It should be completed by late November.